Skip to content

Commit

Permalink
Update Mathematical_notations.rst
Browse files Browse the repository at this point in the history
remove reduplicate symbol
  • Loading branch information
Zhanwei-Liu authored Jul 15, 2023
1 parent 554be60 commit ef0b9e1
Showing 1 changed file with 4 additions and 127 deletions.
131 changes: 4 additions & 127 deletions doc/source/Mathematical_notations.rst
Original file line number Diff line number Diff line change
Expand Up @@ -448,142 +448,19 @@ The cost equations are defined as follows:
.. math::
\rm{cost} &= \rm{cost}_\rm{tech}^\rm{var} + \rm{cost}_\rm{line}^\rm{var} + \rm{cost}^\rm{fuel} + \rm{cost}_\rm{tech}^\rm{fix} + \rm{cost}_\rm{line}^\rm{fix} + \rm{cost}_\rm{tech}^\rm{inv} + \rm{cost}_\rm{line}^\rm{inv} \\
\\
\rm{cost}_\rm{tech}^\rm{var} &= \frac{\sum_{t,m,y,z,\rm{te}}C_{y,z,\rm{te}}^\rm{tech-var}\times \rm{gen}_{t,m,y,z,\rm{te}}}\rm{Weight} \times \rm{factor}_{y}^\rm{var} \\
\rm{cost}_\rm{tech}^\rm{var} &= \frac{\sum_{t,m,y,z,\rm{te}}C_{y,z,\rm{te}}^\rm{tech-var}\times \rm{gen}_{t,m,y,z,\rm{te}}}{\omega} \times \rm{factor}_{y}^\rm{var} \\
\\
\rm{cost}_\rm{line}^\rm{var} &= \frac{\sum_{t,m,y,z_s,z_o}C_{y,z}^\rm{line-var}\times \rm{export}_{t,m,y,z_s,z_o}}\rm{Weight} \times \rm{factor}_{y}^\rm{var} \\
\rm{cost}_\rm{line}^\rm{var} &= \frac{\sum_{t,m,y,z_s,z_o}C_{y,z}^\rm{line-var}\times \rm{export}_{t,m,y,z_s,z_o}}{\omega} \times \rm{factor}_{y}^\rm{var} \\
\\
\rm{cost}^\rm{fuel} & = \frac{\sum_{t,m,y,z,\rm{te}}C_{y,z,\rm{te}}^\rm{fuel}\times \rm{gen}_{t,m,y,z,\rm{te}}}\rm{Weight} \times \rm{factor}_{y}^\rm{var} \\
\rm{cost}^\rm{fuel} & = \frac{\sum_{t,m,y,z,\rm{te}}C_{y,z,\rm{te}}^\rm{fuel}\times \rm{gen}_{t,m,y,z,\rm{te}}}{\omega} \times \rm{factor}_{y}^\rm{var} \\
\\
\rm{cost}_\rm{tech}^\rm{fix} &= \sum_{y,z,\rm{te}}C_{y,z,\rm{te}}^\rm{tech-fix}\times \rm{cap}_{y,z,\rm{te}}^\rm{existing-tech}\times \rm{factor}_{y}^\rm{fix} \\
\\
\rm{cost}_\rm{line}^\rm{fix} &= \sum_{y,z_s,z_o}C_{y,z_s,z_o}^\rm{line-fix}\times \rm{cap}_{y,z_s,z_o}^\rm{existing-line}\times \rm{factor}_{y}^\rm{fix} \\
\\
\rm{cost}_\rm{tech}^\rm{inv} &= \sum_{y,z,\rm{te}}C_{y,z,\rm{te}}^\rm{tech-inv}\times \rm{cap}_{y,z,\rm{te}}^\rm{tech-inv}\times \rm{factor}_{y}^\rm{inv} \\
\\
\rm{cost}_\rm{line}^\rm{inv} &= \sum_{y,z_s,z_o}C_{y,z_s,z_o}^\rm{line-inv}\times \rm{cap}_{y,z_s,z_o}^\rm{line-inv}\times \rm{factor}_{y}^\rm{inv} \times 0.5 \\
\\
The variables are defined as follows:

.. list-table::
:widths: 10 80 5
:header-rows: 1
:align: left

* - Variable
- Description
- Unit

* - :math:`\text{cost}`
- Total cost.
- ``USD``

* - :math:`\text{cost}_\text{tech}^\text{var}`
- Variable cost of technologies.
- ``USD``

* - :math:`\text{cost}_\text{line}^\text{var}`
- Variable cost of transmission lines.
- ``USD``

* - :math:`\text{cost}^\text{fuel}`
- Fuel cost of technologies.
- ``USD``

* - :math:`\text{cost}_\text{tech}^\text{fix}`
- Fixed cost of technologies.
- ``USD``

* - :math:`\text{cost}_\text{line}^\text{fix}`
- Fixed cost of transmission lines.
- ``USD``

* - :math:`\text{cost}_{tech}^{inv}`
- Investment cost of technologies.
- ``USD``

* - :math:`\text{cost}_\text{line}^\text{inv}`
- Investment cost of transmission lines.
- ``USD``

* - :math:`\text{gen}_{t,m,y,z,te}`
- Generation electricity of the :math:`te`-th technology, in the :math:`z`-th zone, in the :math:`y`-th year, for the :math:`m` time period, and in the :math:`t`-th hour.
- ``MWh``

* - :math:`\text{export}_{t,m,y,z_s,z_o}`
- Transmission electricity from the :math:`z_s`-th zone to the :math:`z_o`-th zone, in the :math:`y`-th year, for the :math:`m` time period, and in the :math:`t`-th hour.
- ``MWh``

* - :math:`\text{cap}^\text{existing-tech}_{y,z,te}`
- Existing installed capacity of the :math:`te`-th technology, in the :math:`z`-th zone, and in the :math:`y`-th year.
- ``MW``

* - :math:`\text{cap}^\text{existing-line}_{y,z_s,z_o}`
- Existing transmission capacity from the :math:`z_s`-th zone to the :math:`z_o`-th zone, and in the :math:`y`-th year.
- ``MW``

* - :math:`\text{cap}^\text{tech-inv}_{y,z,te}`
- Newly-build installed capacity of the :math:`te`-th technology, in the :math:`z`-th zone, and in the :math:`y`-th year.
- ``MW``

* - :math:`\text{cap}^\text{line-inv}_{y,z_s,z_o}`
- Newly-build capacity of transmission line from the :math:`z_s`-th zone to the :math:`z_o`-th zone, and in the :math:`y`-th year.
- ``MW``

* - :math:`\text{factor}^\text{var}_{y}`
- Variable cost economic factor in the :math:`y`-th year.
- N/A

* - :math:`\text{factor}^\text{fix}_{y}`
- Fixed cost economic factor in the :math:`y`-th year.
- N/A

* - :math:`\text{factor}^\text{inv}_{y}`
- Investment cost economic factor in the :math:`y`-th year.
- N/A

The parameters are defined as follows:

.. list-table::
:widths: 10 80 5
:header-rows: 1
:align: left

* - Parameter
- Description
- Unit

* - :math:`C_{y,z,te}^\text{tech-var}`
- Variable cost of unit capacity of the :math:`te`-th technology, in the :math:`z`-th zone, and in the :math:`y`-th year.
- ``USD/MW``

* - :math:`C_{y,z}^\text{line-var}`
- Variable cost of unit capacity of transmission line in the :math:`z`-th zone, and in the :math:`y`-th year.
- ``USD/MW``

* - :math:`C_{y,z,te}^\text{fuel}`
- Fuel cost of unit generation electricity of the :math:`te`-th technology, in the :math:`z`-th zone, and in the :math:`y`-th year.
- ``USD/MWh``

* - :math:`C_{y,z,te}^\text{tech-fix}`
- Fixed cost of unit capacity of the :math:`te`-th technology, in the :math:`z`-th zone, and in the :math:`y`-th year.
- ``USD/MWy``

* - :math:`C_{y,z_s,z_o}^\text{line-fix}`
- Fixed cost of unit capacity of transmission line from the :math:`z_s`-th zone to the :math:`z_o`-th zone, and in the :math:`y`-th year.
- ``USD/MWy``

* - :math:`C_{y,z,te}^\text{tech-inv}`
- Investment cost of unit capacity of the :math:`te`-th technology, in the :math:`z`-th zone, and in the :math:`y`-th year.
- ``USD/MW``

* - :math:`C_{y,z_s,z_o}^\text{line-inv}`
- Investment cost of transmission lines from the :math:`z_s`-th zone to the :math:`z_o`-th zone, and in the :math:`y`-th year.
- ``USD/MW``

* - :math:`\text{Weight}`
- Proportion of selected scheduling period in a year (8760 hours) that is :math:`\frac{H\times M}{8760}`.
- N/A
\rm{cost}_\rm{line}^\rm{inv} &= \sum_{y,z_s,z_o}C_{y,z_s,z_o}^\rm{line-inv}\times \rm{cap}_{y,z_s,z_o}^\rm{line-inv}\times \rm{factor}_{y}^\rm{inv} \times 0.5